Laporan Keuangan Pembangunan Masjid An-Nubuwwah per 30 Mei 2015, sebagai berikut:
PENERIMAAN MAL INFAQ
NO |
KETERANGAN |
TOTAL (Rp) |
1 |
LAMPUNG |
295.072.525,00 |
2 |
Markas II MUHAJIRUN |
301.667.622,00 |
3 |
JABODETABEK |
215.644.000,00 |
4 |
JAWA BARAT |
220.964.500,00 |
5 |
JAWA TENGAH UTARA |
100.000.000,00 |
6 |
JAWA TENGAH SELATAN |
146.100.000,00 |
7 |
SUMATERA SELATAN |
38.136.000,00 |
8 |
SUMATERA UTARA & NAD |
500.000,00 |
9 |
JAMBI |
61.700.000,00 |
10 |
KALIMANTAN BARAT |
93.750.000,00 |
11 |
KALIMANTAN TIMUR |
89.500.000,00 |
12 |
INDONESIA TIMUR |
1.706.000,00 |
13 |
MALAYSIA |
50.677.925,00 |
14 |
Markaz I CILEUNGSI |
78.366.575,00 |
15 |
THAILAND |
5.325.000,00 |
16 |
Donatur Dari ketua MPR |
37.618.000,00 |
17 |
Donatur Dari Kantor Kecamatan Natar |
12.430.000,00 |
18 |
Pendengar Rasil AM 720 |
151.000.000,00 |
19 |
Hamba Allah (setor tunai) |
187.368.820,00 |
20 |
Hamba Allah (transfer Bank) s/d 30 Mei |
675.145.500,00 |
|
TOTAL PEMASUKAN |
Rp 2.798.592.867,00 |
PENGGUNAAN MAL
NO |
PENGELUARAN |
JUMLAH (Rp) |
1 |
Pembelanjaan Material |
1.170.996.219,00 |
2 |
Transportasi |
82.929.200,00 |
3 |
Biaya Jasa |
389.810.200,00 |
4 |
Upah Kerja Tukang |
129.295.000,00 |
5 |
Bisaroh Staff Kantor |
66.100.000,00 |
6 |
Konsumsi |
38.594.200,00 |
7 |
Akomodasi |
27.088.700,00 |
8 |
Percetakan |
6.772.000,00 |
9 |
Lain-Lain |
9.278.000,00 |
10 |
ATK |
6.144.000,00 |
11 |
Peralatan Kantor |
43.499.000,00 |
12 |
Penggalangan Dana |
43.823.449,00 |
13 |
Acara Ground Breaking |
181.248.585,00 |
14 |
Listrik, Air, Telephone |
20.086.264,00 |
|
TOTAL PENGELUARAN |
2.215.664.817,00 |
SALDO SAMPAI 30 Mei 2015 adalah sebesar
Rp 582.928.050,00